Kim Eslinger
Editor
612-321-8040
kim@millcitymedia.org

Brianna Ojard
Associate Editor

David Tinjum
Publisher
612-321-8020
dave@millcitymedia.org

Claudia Kittock
Columnist / Non-Profits
Email Claudia...

Becky Fillinger
Small Business Reporter
Producer / Milling About
Email Becky...

Michael Rainville Jr.
History Columnist
Email Michael...

Doug Verdier
River Matters

Mill City Times is a not-for-profit community service. We do not sell advertising on this site.

Community Partners

Thanks to our community partners, whose support makes Mill City Times possible:

MILL CITY FARMERS MARKET

With over 100 local farmers, food makers and artists, MCFM strives to build a local, sustainable and organic food economy in a vibrant, educational marketplace.

Visit their website...

HENNEPIN HISTORY MUSEUM

Hennepin History Museum is your history, your museum. We preserve and share the diverse stories of Hennepin County, MN. Come visit!

Visit their website...

MEET MINNEAPOLIS

Maximizing the visitor experience of Minneapolis for the economic benefit of our community, making Minneapolis the destination of choice among travelers.

Visit their website...

MSP FILM SOCIETY

Promoting the art of film as a medium that fosters cross-cultural understanding, education, entertainment, and exploration.

Visit their website...

GREAT RIVER COALITION

Enhancing the Minneapolis riverfront environment—for people and pollinators.

Visit their website...

Cultural Cornerstones
Search Mill City
Recent News
Front Page Archives
Wednesday
Oct262022

October 26 Bridge 9 Improvement Project Update

Bridge No. 9 was constructed in 1922 by the Northern Pacific Railroad to carry freight over the Mississippi. The City of Minneapolis acquired this bridge in 1986 and converted the bridge to a pedestrian use bridge in 1999. The bridge currently provides a Mississippi River crossing for the Dinkytown Greenway bike trail.

Beginning in July 2022, the City of Minneapolis started making repairs and improvements to Bridge 9, Pier 5.

Latest project news

Construction Update Meeting (online meeting)

Virtual monthly project stakeholder meetings were held at 9:30 am the 1st Thursday of each month using Microsoft Teams. These meeting have been suspended until the Spring of 2023 as Pier 5 work nears completion. The meetings will resume when the Contractor prepares to begin Pier 2 and Abutment 1 work on the easterly side of the river next year.

Join on your computer or mobile app.

Click here to join the meeting

Or join by entering a meeting ID Meeting ID: 213 161 635 706 Passcode: KyceBr

Or call in (audio only)

+1 612-428-8778,,6668421#   United States, Minneapolis

Phone Conference ID: 666 842 1#

These meetings help us to give you more detailed information about work progress on a monthly basis and to have discussion on any concerns or questions you have about the project. Please send an email or give a call to the project engineer if you have difficulty using the link above.

If no one joins the meeting within 10 minutes the meeting will end, but you can still contact the meeting coordinator via phone or email:

Rich Revering, Design Team Project Manager; 612-718-8412 or Richard.Revering@Bolton-Menk.com

Schedule

Construction activities for Pier 5 repairs started in July 2022. The scheduled completion date is December 1, 2022. The contractor is currently anticipating substantial completion by the end of October 2022. 

Traffic Impact

West River Parkway is scheduled to be open for vehicular traffic subject to occasional one-way traffic w/ flaggers during certain equipment and material loading operations. Pedestrian and bicycle traffic are open to traffic, with pedestrians sharing the bike path through the project area

Current work

For the month of October, the following construction operations were performed: Forming and pouring pier wrap foundations and four lifts of pier wrap. The wrap is a thick layer of reinforced concrete to contain and strengthen the pier to extend its useful life. Current work involves placing an overlay over the bridge seat, concrete touch ups as needed, grading, riprap, and site restoration and cleanup.

Coming up

Work will be suspended on the bridge until next spring. Normal bicycle and pedestrian patterns will resume when construction is suspended.

Stay Connected

For more details and to sign up for email updates please visit the Bridge 9 Improvement project webpage.

Project Engineer: Petru Vizoli, 612-673-2368, Petru.Vizoli@minneapolismn.gov