Maintenance on 5 Bridges Along I-94 Begins This Fall
Beginning in fall 2024 through fall 2025, MnDOT crews will conduct bridge preservation and maintenance work on five bridges along I-94 in Minneapolis. These bridges include:
- I-94 bridge (Dartmouth Bridge) that spans the Mississippi River
- Riverside Ave. bridge over I-94
- I-94 over Cedar Ave.
- I-94 over the Light Rail Transit (Blue Line)
- I-94 over Hwy 55/Hiawatha Ave.
Summary of work
- Construct temporary crossovers
- Repair bridge decks
- Resurface bridge pavement
- Remove and replace bridge joints
- Update guardrails
- Upgrade drainage
- Repaint bridge steel
Information about upcoming traffic impacts will be posted as details become available. Motorists can expect overnight lane closures on I-94 between downtown Minneapolis and the Franklin Avenue Bridge over I-94 in fall 2024. During construction in 2025, motorists can expect I-94 to be reduced to two lanes in each direction between Hwy 55/Hiawatha Ave. and the Franklin Avenue Bridge over I-94.
Sign up to receive project email updates at mndot.gov/metro/projects/i94minneapolis.