April 6 Minneapolis Central City Tunnel Project Update
Via an April 6 e-announcement from the City of Minneapolis:
The City of Minneapolis Public Works Department is constructing a new parallel storm tunnel, enlarging a portion of the existing storm tunnel, and constructing a new tunnel access in Downtown Minneapolis. This project is anticipated to be completed summer 2023.
The new tunnel is being constructed parallel to the existing tunnel located under Washington Ave S between Nicollet Mall and Chicago Ave. The existing tunnel under Chicago Ave between Washington Ave S and the Mississippi River is being expanded to handle the increased stormwater capacity. The purpose of this project is to reduce pressure in the existing tunnel, provide more room for future growth, and to reduce the need for future repairs and tunnel failures.
Project Map
Latest Project News
Hennepin Ave
- Tunneling the new parallel storm tunnel under Washington Ave continues. You will see crews continue excavating soils from the existing tunnel access shaft at the northeast corner of the Washington Ave and Hennepin Ave intersection. This is to tunnel the new parallel storm tunnel under Washington Avenue.
- There may be short, periodic delays while crews move equipment and materials around.
2nd Ave
- Crews continue tunneling the new parallel storm tunnel under Washington Avenue from the new tunnel access shaft in the southbound lanes of 2nd Ave S, just north of the Washington Ave intersection.
- The sidewalks remain open on both sides of the road.
- The crosswalk at the Washington Ave and 2nd Ave S intersection remains open.
- 2nd Ave S remains a single lane in each direction using the northbound lanes between Washington Ave and 1st St S.
- Access to driveways off 2nd Ave S remain open. There may be short-term access delays while crews move equipment and materials around.
Portland Ave
- Tunneling the new parallel storm tunnel under Washington Ave continues from the existing tunnel access shaft at the northeast corner of the Washington Ave and Portland Ave intersection.
- There may be short, periodic delays while crews move equipment and materials around.
Mississippi River Portal
- Crews continue excavating soils above the storm sewer tunnel and grouting near the existing retaining wall at the Mississippi River portal site through April 2022. Work will resume fall 2022.
- The parking lot off Portland Ave east of the Stone Arch Bridge, near Mill Ruins Park, will reopen in early May 2022.
- This lot is currently closed to complete work in this area safely and efficiently.
- The parking lot near Portland Ave and W River Pkwy remains open.
What to Expect
- Expect additional noise, dust, and vibration as crews complete work.
- Schedule is tentative and subject to change due to weather and other unforeseen circumstances
Long-term closures/restrictions
- The north westbound lane, bike lane, and parking lane remains closed on Washington Ave between Portland Ave and Park Ave. These closures will remain in place until the project completed. This is necessary for the contractor to utilize the existing shaft to connect the existing tunnel to the new tunnel.
- During this closure, pedestrians can still use the sidewalks along Washington Ave.
- Crosswalks across Washington Ave and Portland Ave will remain open.
- Bicyclists will share the traffic lane.
- The existing left turn lane on Washington Ave at the Portland Ave intersection will temporarily become a left turn and through lane.
- The north sidewalk along Washington Ave remains closed between Hennepin Ave and Nicollet Mall through spring 2022. The contractor is utilizing an existing shaft in this area to connect the existing tunnel to the new tunnel.
- During this closure, pedestrians share the bike lane on Washington Ave.
- The crosswalks at the Washington Ave intersections of Nicollet Mall and Hennepin Ave remains open.
- The sidewalk on the east side of 4th Ave S remains closed through spring 2022. The dewatering well and pumps are installed in this area.
- The sidewalk on the east side of 4th Ave S remains closed.
- Pedestrians can use the sidewalk on the west side of 4th Ave S.
- The crosswalk at the Washington Ave and 4th Ave intersection remains open.
- Access to driveways off 4th Ave S remains open.
- The eastern sidewalk along Nicollet Mall between Washington Ave and 3rd St N is closed through spring 2022. Access is open to the Marquette Plaza building. The dewatering well and pumps are installed in this area.
- Pedestrians are still able to use the sidewalk on the west side of Nicollet Mall.
- The crosswalk at the Washington Ave intersection remains open.
- The west sidewalk of Portland Ave south of Washington Ave will remain restricted to pedestrians around the dewatering well and pumps until the project is completed.